How Siemens young engineers used talent & digital tools to make history

Posted on 27 Jul 2020 by Jonny Williamson

Apprentices and young engineers at Siemens have become part of manufacturing history after playing a major role in the VentilatorChallengeUK consortium producing 13,500 medical devices in just 12 weeks.

In total, a team of 100 people from Siemens UK, Digital Industries (DI), Industry Software, Siemens Healthineers and Siemens Energy contributed to VentilatorChallengeUK, including apprentices and young engineers at the very start of their careers with Siemens.

From their kitchens and bedrooms, they helped design and build a factory from scratch and scale production from 10 ventilators to 1,500 a week.

Using Siemens’ digital enterprise portfolio, they were able to design, validate and deliver a sub-assembly factory with manufacturing capacity for 1,500 ventilators a week within four weeks, against an industry norm of more than 12 months.


Siemens team at AMRC Broughton

Siemens team at AMRC Broughton


Led by Andrew Peters, managing director of Siemens’ digital factory in Congleton, the first major achievement by the team was to create a digital twin of the Airbus AMRC Cymru in Broughton (one of seven new large-scale manufacturing facilities needed by the consortium) within 48-hours.

Simulation software played a key role in optimising the layout of the factory, reducing the physical footprint of the production lines and workstations from initial estimations of 90 to 30 – a 66% saving.

It was also used to determine the fastest and most efficient build sequence and reduced the number of people required.

Ben Apps (28), plant layout and virtualisation engineer at Siemens Congleton, said: “Not only did we have to find a solution to enable us to ramp up production from 10 ventilators, we had to use multiple production lines and ensure social distancing of the hundreds of operators. 

“By creating a digital twin of the AMRC, mapping every inch of the available space, calculating all throughput, and using 3D design tools, we were able to maximise production massively.

“What was also remarkable was that digital tools enabled us to design the production line virtually in six days, saving thousands of pounds and hours in the real world.”

Ventilator production lines at the AMRC
Ventilator production lines at the AMRC

Digital tools also enabled Siemens to convert 3D CAD data in Cortona to allow product and process visualisation in a standard web browser. This enabled the rapid training of 550 Airbus volunteer operators within two weeks.

Matt Danby (24), a production engineer at Siemens Congleton, was tasked with developing the fastest and most efficient build sequence and training the operators.

He explained: “The ventilator is a complicated product with 400 individual parts. To design a brand-new build sequence would normally take anywhere between six to 12 months. We managed it in two weeks which is staggering.

“We were also able to incorporate digital work instructions that played an animated work sequence which allowed the operator to change the viewing angle, pause and see the products virtually in snapshots. It helped speed up the training process.”

Elliot Bloor, a Higher Industrial engineering Apprentice at Siemens Congleton, worked on the timings for production.

He explained: “Our starting point was a video from building a ventilator. We had to break that down into chunks and take timings. We put that data into Siemens’ Plant Simulation software.

“From that we could determine how many ventilators we could make in a day or week, and how many operators we’d need to make them. That simulation allowed us to be able to say to partners and the government how many we could build and what we needed to build it.”

Once manufacturing had started, Siemens DI also drafted in 11 of its young engineers to solve a problem which was slowing up assembly of a key component of the ventilator.


Siemens - Using a four-day hackathon, and under strict social distances measures, the group used software to design, simulate, build and test a manufacturing aid that helped reduce the calibration time from 40 minutes to two.

Using a hackathon, the group helped reduce the calibration time from 40 minutes to two


Using a four-day hackathon, and under strict social distances measures, the group – which included Michal Zlotek; Joe Tasker; Zack Brown; Ben Parry, Liv Kelly; Matt Clarkson; Ryan Durbridge; Anubhi Khandelwal; Connor Hendry; Jess Reading; Elliot Baskerville; Gabriel Vijent, and John Mackey – used software to design, simulate, build and test a manufacturing aid that helped reduce the calibration time from 40 minutes to two.

The team even went one step further and designed a fully automated solution with the potential to cut the calibration time to just two seconds. 

Reflecting on the achievement Brian Holliday, managing director, Digital Industries, Siemens UK and Ireland, said: “The VentilatorChallengeUK has been a project of extreme collaboration. This was achieved with ownership culture and leadership without ego. Internal divisions and competitor norms were carefully set aside for the greater good for society.

“Long hours were worked, sometimes away from families, often from home under lockdown but the team remained focused and passionate knowing that every ventilator produced can save a life.”


*All images courtesy of Siemens