Tasked with the design and installation of a bespoke ventilation system for Royal Mail Parcelforce, Colt discusses how its custom solution significantly reduced operating costs.
The client:
Royal Mail Parcelforce
The brief:
Colt was asked to design and install a ventilation system for Parcelforce’s sorting and distribution centres to control exhaust emissions from the delivery vans.
The situation:
The sorting and distribution centres are converted warehouses and can contain up to 150 vans at any one time, all entering and exiting the building at similar times.
Design considerations:
The standard prescriptive solutions in Approved Document F for exhaust emissions focus on the air change rate, which in the case of Parcelforce’s sorting centres would have meant 6 air changes per hour.
However, this rate would not take into account the variations in the levels of diesel exhaust in the air at different times.
There would be peaks at the times vans drive in or out, but levels would go down when they were stationary while loading or unloading the parcels, or when the building was empty between rounds of deliveries and collections.
The solution:
Colt developed a system which achieves cross flow ventilation via natural inlet air and mechanical extract with a combination of axial fans and natural ventilators.
These are triggered by CO detectors when emissions levels reach a pre-determined level. This means that mechanical extraction fans only operate when needed, significantly cutting operating costs.
The benefits:
This outside-of-the-box approach is extremely cost effective and is significantly cheaper than the prescriptive solutions.
However, this solution was only possible due to Colt’s early involvement with the customer, which enabled the business to support the M&E consultant from initial design through to approval with building control.
Read the full case history here.
Royal Mail were able to tell Colt when and how the van movements occurred with specifics in terms of roadways and bay layouts, which allowed us to tailor the design.
This solution was repeated over several buildings, all completed simultaneously, allowing Royal Mail to achieve continuity over design and systems installed.